Recycled Paper COLD Cup Lead Time

NEW!
BASIC 1:2
Program
Recycled Paper COLD Cup Lead Time

Double Wall Paper Cups

DESCRIPTION GLOSSMATTE SCHEDULE AVAILABLE RUSH RUSH CHARGE
9 oz X2D9XHD9 5 Working Days 3-Day & 4-Day 3-Day $62.50/v, 4-Day $50/v
12 oz X2D3XHD3 5 Working Days 3-Day & 4-Day 3-Day $62.50/v, 4-Day $50/v
16 oz X2D6XHD6 5 Working Days 3-Day & 4-Day 3-Day $62.50/v, 4-Day $50/v
21 oz X2D2XHD2 5 Working Days 3-Day & 4-Day 3-Day $62.50/v, 4-Day $50/v

Production Run Cutoff and Ship Dates

DESCRIPTIONCODESCHEDULENEXT RUN
CUTOFF
NEXT
SHIP DATE
CUTOFF
2
SHIP
2
CUTOFF
3
SHIP
3
CUTOFF
4
SHIP
4
9 ozC909WeeklyMon
02/24
Thu
03/05
Mon
03/02
Thu
03/12
Mon
03/09
Thu
03/19
Mon
03/16
Thu
03/26
Tall 12 ozC613WeeklyTue
02/25
Fri
03/06
Tue
03/03
Fri
03/13
Tue
03/10
Fri
03/20
Tue
03/17
Fri
03/27
Tall 16 ozC616WeeklyMon
02/24
Thu
03/05
Mon
03/02
Thu
03/12
Mon
03/09
Thu
03/19
Mon
03/16
Thu
03/26
17 ozC617WeeklyTue
02/25
Fri
03/06
Tue
03/03
Fri
03/13
Tue
03/10
Fri
03/20
Tue
03/17
Fri
03/27
20 ozC920Bi-WeeklyTue
03/03
Fri
03/20
Tue
03/17
Fri
04/03
Tue
03/31
Fri
04/17
Tue
04/14
Fri
05/01
Tall 21 ozC621Bi-WeeklyTue
02/25
Fri
03/13
Tue
03/10
Fri
03/27
Tue
03/24
Fri
04/10
Tue
04/07
Fri
04/24
24 ozC924Bi-WeeklyThu
03/05
Tue
03/24
Thu
03/19
Tue
04/07
Thu
04/02
Tue
04/21
Thu
04/16
Tue
05/05
32 ozC932Bi-WeeklyThu
03/05
Tue
03/24
Thu
03/19
Tue
04/07
Thu
04/02
Tue
04/21
Thu
04/16
Tue
05/05
44 ozC944Bi-WeeklyWed
03/04
Mon
03/23
Wed
03/18
Mon
04/06
Wed
04/01
Mon
04/20
Wed
04/15
Mon
05/04

Updated February 21, 2020

Our standard lead time is one to four weeks depending on volume, when the order is placed, and the product being ordered. Each cup has a regular production schedule and all orders must be placed by the scheduled CUTOFF day. Quantities up to 50,000 pieces are available in the standard production run. Lead-time for larger orders are reviewed and approved on a case-by-case basis.


How do the Weekly Production Runs work?

As shown above, each cup has a regular production run with two critical days. These are:

RUN CUTOFF Day is the last day we accept orders for the current production run without a LATE charge. All order details including art approval and any deposits, if required, must be finalized by 12:00pm PST on the day after the RUN CUTOFF Day. Orders submitted the day after the RUN CUTOFF day may still be eligible for the current production run with a $120/v late charge. To be eligible, all order details including art approval and any deposits, if required, must be finalized by 12:00pm PST. If approvals and deposits are not received by 12:00pm PST on this day, the order will miss the current production run and will have to wait for the next production run.

SHIP Day is the day the order ships. Orders can be scheduled to ship AFTER the run's SHIP Day but not before.

What RUSH options are available?

None. An order that is complete and can run without additional approvals, deposits, questions, and instructions can be placed by 12:00pm PST the day after the Production Run's CUTOFF day and will incur a $120/v LATE charge.