Paper COLD Cup Lead Time

Everything Green Progress:
09 13 16 17 20 21 24 30 32 44
All Cold Cup sizes have transitioned to 32% PCF
NEW!
BASIC 1:2
Program
Paper COLD Cup Lead Time

Double Wall Paper Cups

DESCRIPTION CODE SCHEDULE AVAILABLE RUSH RUSH CHARGE
9 oz X2D9 5 Working Days 3-Day & 4-Day 3-Day 62.50/v, 4-Day $50/v
12 oz X2D3 5 Working Days 3-Day & 4-Day 3-Day 62.50/v, 4-Day $50/v
16 oz X2D6 5 Working Days 3-Day & 4-Day 3-Day 62.50/v, 4-Day $50/v

Production Run Cutoff and Ship Dates

DESCRIPTIONCODESCHEDULENEXT RUN
CUTOFF
NEXT
SHIP DATE
CUTOFF
2
SHIP
2
CUTOFF
3
SHIP
3
CUTOFF
4
SHIP
4
9 ozC909WeeklyMon
07/15
Tue
07/23
Mon
07/22
Tue
07/30
Mon
07/29
Tue
08/06
Mon
08/05
Tue
08/13
Tall 12 ozC913WeeklyTue
07/16
Wed
07/24
Tue
07/23
Wed
07/31
Tue
07/30
Wed
08/07
Tue
08/06
Wed
08/14
Tall 16 ozC916WeeklyMon
07/15
Tue
07/23
Mon
07/22
Tue
07/30
Mon
07/29
Tue
08/06
Mon
08/05
Tue
08/13
17 ozC917WeeklyTue
07/16
Wed
07/24
Tue
07/23
Wed
07/31
Tue
07/30
Wed
08/07
Tue
08/06
Wed
08/14
20 ozC920Bi-WeeklyTue
07/23
Wed
08/07
Tue
08/06
Wed
08/21
Tue
08/20
Wed
09/04
Tue
09/03
Wed
09/18
Tall 21 ozC921WeeklyTue
07/16
Wed
07/24
Tue
07/23
Wed
07/31
Tue
07/30
Wed
08/07
Tue
08/06
Wed
08/14
24 ozC924Bi-WeeklyThu
07/25
Fri
08/09
Thu
08/08
Fri
08/23
Thu
08/22
Fri
09/06
Thu
09/05
Fri
09/20
30 ozC9304-WeekThu
07/25
Fri
08/09
Thu
08/22
Fri
09/06
Thu
09/19
Fri
10/04
Thu
10/17
Fri
11/01
32 ozC932WeeklyThu
07/18
Fri
07/26
Thu
07/25
Fri
08/02
Thu
08/01
Fri
08/09
Thu
08/08
Fri
08/16
44 ozC944Bi-WeeklyWed
07/24
Thu
08/08
Wed
08/07
Thu
08/22
Wed
08/21
Thu
09/05
Wed
09/04
Thu
09/19

Updated July 15, 2019

Our standard lead time is one to four weeks depending on volume, when the order is placed, and the product being ordered. Each cup has a regular production schedule and all orders must be placed by the scheduled CUTOFF day. Quantities up to 50,000 pieces are available in the standard production run. Lead-time for larger orders are reviewed and approved on a case-by-case basis.


How do the Weekly Production Runs work?

As shown above, each cup has a regular production run with two critical days. These are:

RUN CUTOFF Day is the last day we accept orders for the current production run without a LATE charge. All order details including art approval and any deposits, if required, must be finalized by 12:00pm PST on the day after the RUN CUTOFF Day. Orders submitted the day after the RUN CUTOFF day may still be eligible for the current production run with a $120/v late charge. To be eligible, all order details including art approval and any deposits, if required, must be finalized by 12:00pm PST. If approvals and deposits are not received by 12:00pm PST on this day, the order will miss the current production run and will have to wait for the next production run.

SHIP Day is two weeks after the RUN CUTOFF Day. Orders can be scheduled to ship AFTER the run's SHIP Day but not before.

What RUSH options are available?

None. An order that is complete and can run without additional approvals, deposits, questions, and instructions can be placed by 12:00pm PST the day after the Production Run's CUTOFF day and will incur a $120/v LATE charge.